2022.06.08 Our company received an instruction from Pakistan to install a set of radomes with a diameter of 20 meters in Mangla.
The climatic and environmental conditions in this area are extremely harsh. From April to September every year, there are strong winds of more than 30 knots, and the instantaneous wind speed can reach 70 knots, which brings a lot of inconvenience to the erection of the radome. Since we have agreed to the customer's request, we must complete the task with quality and quantity.
The most critical and most dangerous time is when the single unit is installed to the fourth floor. If you continue to install it upwards, if you encounter strong winds, all your efforts will be lost. Just when the installation team hesitated, our company set up an emergency team, which was deployed and commanded by Mr. Geng personally. Business and technology kept communicating with the scene through video. We divided the installation team into two groups and carried out the installation work simultaneously from both sides of the cover. Speed up the installation process when the wind is small, and reinforce each piece to ensure that a full circle of installation and reinforcement must be completed every day, and no rest if not completed.
For ten sleepless nights in a row, we challenged the high temperature of more than 40 degrees during the day, and we raced against the strong wind at night, and finally successfully capped it on 2022.06.13, and ended the game on 2022.06.18.
We completed the installation and sealing of the 20m radome in just 10 days. It's incredible! I like the pragmatism and efficiency of the company!